Hi Experts,
We have a requirement to stop system from generating planned orders within SNP Horizon in the light of Christmas vacations.
I understand that SNP doesn't read resource downtime, thus in order to achieve this, we added special rule to the calendar assigned to the respective resource such that resource is not available during the stipulated time.
In addition to this, we also created a time stream ID based on the calendar and assigned it to production calendar at location. Now, when I take a planning run, system created a planned order just outside the vacation duration, with a start date within the vacation which is not desired.
When we convert the SNP order to PP/DS the start date correctly falls outside the vacation, not sure why this is happening.
Any idea how this can be controlled?
Many thanks in advance.
Regards,
Rishi