Hello Guru,
I am facing a issue while running the heuristics method of capacity leveling in SNP
When I ran the capacity leveling I am getting a below warning message and all the orders are moved to the end of the planning period.
Order cannot be created in the production horizon
Message no. /SAPAPO/MSDP_CAP110
Example Data:
I have orders in Week 31 of 2016 for 1000 Pcs and Week 45 of 2016 for 1000 pcs
Capacity overload : 200% for week 31 of 2016
After Capacity leveling is executed Both the orders are moving to last week of the planning horizon ( Data view). In these case to Week 27 of 2017
Before Capacity Leveling:
After Capacity Leveling:
Could you please anyone help on the above issue.
Thank you in Advance
Srikanth